Barstow Bridge Replacement Project, CRP 777 |
| |
|
Location: M.P. 0.01 to M.P. 0.04
|
| |
|
|
|
|
|
Prime Contractor:
Harcon Inc., Spokane, WA |
|
|
|
Scope of Work: |
|
|
|
Project scope of work involves
clearing and grubbing, pulverizing existing pavement, excavation and
embankment, removal of existing bridge and pier, Construction footings
on piles on Ferry County side and spread footing on Stevens County side,
constructing pre-cast concrete bridge, placement of crushed surfacing, placement of Hot Mix Asphalt,
installation of guardrail, erosion control, and traffic control.
|
|
Total Working Days:
244 |
|
|
|
This weeks Project Status: (Week of 5/16/11) |
|
- Contractor will place top course on bridge approaches
and main roads. |
|
- Contractor will place membrane on bridge deck. |
|
- Contractor will pave bridge approaches and main roads. |
|
- Contractor will begin installing guardrail. |
|
- Contractor will continue to trimming and cleanup
project in anticipation of opening. |
|
|
|
Traffic Information: |
|
|
|
- A detour is in place which routes traffic down the Kettle River Road to Napoleon Bridge and
across to US 395. Click here for map. |
|
- Residents living in area of construction will have
access to homes. |
| |
| Working Days
Left: (As of May 16th, 2011) |
|
|
|
29 |
| |
| Anticipated Completion Date:
June 17th, 2011 |